Home : Site Map : Print
 
Escambia County, Florida
www.myescambia.comg 
Building Inspections

Inspections - What is checked during a building inspection

What do you check during a building inspection?

On this page you will find listings for a few of the building inspection types. The items, though not all inclusive, are listed to illustrate the types of things that are checked. Because each project is different, your inspector may inspect only those items listed for a particular inspection, or may look for things that are not on the list. When in doubt about what the inspector will check, ask them before they visit your site.

The building inspectors are the "eyes and ears" of the County's Building Official in the field. It is their responsibility to ensure that each building constructed, each addition built, and every renovation completed complies with all applicable codes. For that reason, our inspectors are responsible for identifying and reporting any problem they may find, whether it is in their field or not.

The Basics


Every time an inspector arrives at a job site for an inspection, there are some basic things that are checked. You may consider the things on this list "housekeeping" issues, that are fundamental requirements which, by themselves, can be cause for rejection. Once you have complied with "the basics", what other types of things will we be looking for?

• Verify that approved plans are on the job-site.
• Verify that the building card is properly posted and protected from the elements.
• Verify that the "Notice of Commencement" is posted.
• Verify that the configuration of the structure matches the plans.
• Verify proper sanitary facilities are on-site.
• Verify proper setbacks from all property lines and/or from adjacent structures.

1. Footing Inspection
• Verify depth and width of footings. (Ditches must be square, clean, and dry.)
• Verify that step downs are properly headered off.
• Verify that grade stakes are correct.
• Verify steel configuration and size match approved plans. (NOTE: Minimum 3" clearance sides and bottom. Steel shall be free of foreign matter and securely tied. Minimum lap 25".)
• Verify finish floor height to determine if vertical steel will be required. (NOTE: Stem walls 5 blocks high or higher require footing and stem walls to be designed and sealed by a registered architect or engineer.)
• Verfy that interior area of future fill for slab is free of all organic matter and is ready for fill dirt.

2. Slab Inspection
• Verify that compaction of fill dirt is correct. (NOTE: Footings on fill dirt require compaction report.)
• Verify that termite treatment has been done and sign is posted.
• Verify that proper vapor barrier is in place.
• Verify that rough inspections for any plumbing, mechanical, and electrical under slab work have passed and appropriate stickers are in place.
• If stem walls exceed 4 1/2 blocks, approved sealed drawings by a registered architect are required.
• Verify that depth of concrete will not be less than 3 1/2" at any place in slab.
• Verify that any required grade beams are in place. (NOTE: Grade beam footings that do not extend to natural grade require compaction test.)

3. Monolithic Slab Inspection
• Verify depth and width of footing (ditches must be square, clean, and dry.)
• Verify that wire mesh is in place and lapped properly. If fiber mesh is to be used, inspector will make a notation on the blue card and in the computer.

4. Framing Inspection
• Review windload calculations for specific requirements, then verify: Sole plate attachments are in place, Correct stud spacing, Correct header sizes.
• Glass in hazardous locations is correct. (i.e., 24" radius from door edge in closed position.)
• Required second means of escape are in place and correct.
• Required plumbing stack-out, gas, mechanical, and electrical inspections are completed and tagged properly.
• Top plate penetrations are properly sealed with an approved material.
• Attic access is correct, minimum 22 1/2" X 36". (NOTE: Entire attic must be accessible. A vaulted ceiling may necessitate an additional access.)
• Fire blocking is in place. (i.e., vaulted ceilings, furred down areas, etc.)
• Supports for beams, trusses, headers, etc. are addequate.
• Proper hurricane clips and truss hangers are in place.
• Required connectors from sole plate to stud and stud to top plate are installed per windload calculations.
• Gable wind braces are in place.
• Required truss bracing is in place per manufacturer's design and required windload calculations.
• Over-roof rafters and trusses are blocked and strapped properly to trusses below deck line.
• Collar ties are in place where required and properly spaced.
• Garage door header is properly designed and installed per approved design.
vExterior sheathing is nailed and installed per windload requirements.
• Roof Sheathing is nailed and installed per windload requirements.
• Brick ties, where applicable, are installed properly.
Proper weatherproofing on all exterior walls and openings has been done per requirements of specific exterior wall finish.

5. Roofing Inspection

• Verify all types of roof coverings are installed on proper roof slopes.
• Verify that nails and fasteners are installed appropriately for the roofing system.
• Verify all roofs are flashed and sealed at all valleys, rakes, penetrations, and all vertical projections.
• Verify that type of roofing material meets code requirements.

Copyright © 2003 Escambia County, FL
Site Design by CED
Home | Website Contact | Legal Notice | Privacy Policy